City of Vancouver
Information Bulletin
July 15, 2016
Temporary
pathway installation gets under way next week
The removal of train rails
and ties from the Arbutus Corridor was substantially completed this week, ahead
of schedule. This paves the way for the City to proceed, starting next week,
with installation of a temporary asphalt pathway to allow continued use of the
space for recreation until construction of the future Arbutus Greenway gets
under way.
Canadian Pacific Railway
Ltd. (CP) was responsible for all rail removal along the corridor, with the
exception of street crossings, as part of the City’s land purchase agreement
announced in March 2016. A total of 17 kilometers of rail and 16,000 ties were
removed.
The City is responsible for
removing the rails at street crossings, work which will be completed at a later
date.
The temporary pathway,
which will be shared by pedestrians and those riding bikes or on rollerblades,
etc. will be installed in sections; the first phase from Fir Street to 41st
Avenue is expected to be complete by the end of Summer 2016. The pathway will
eventually extend all the way south from 41st Avenue to Marpole. The City will advise residents when the
pathway is open for recreation use. Permitted use of the temporary pathway will
include walking, cycling, rollerblades and push scooters. No motorized vehicles
or scooters will be allowed.
Pathway installation work
will take place during City construction hours: 7 a.m. to 8 p.m. Monday to
Saturday, and 10 a.m. to 8 p.m. Sundays and holidays. The public is asked to
continue to use caution near construction areas, obey all signage and to use
extra caution when crossing roadways.
The Arbutus
Greenway project office is expected to be fully staffed and operational by the
end of summer 2016. Public consultation on the plans for the new public
transportation greenway is expected to begin in the fall.
The public can
get more information about the plans for the Arbutus Greenway, watch a video tour of the greenway route as it is today, or sign up for email updates by
visiting the City’s website: vancouver.ca/arbutus-greenway.
-30-